The West Tunnels Journey

CrosstownTO - Published on May 10, 2016

Tunnelling from Black Creek Drive began in June 2013. The west tunnel boring machines have travelled 6.419 kilometres. Each machine installed 25, 647 precast concrete tunnel segments, which formed 4,279 rings.